SEVERAL major roadworks programmes are set to start in Somerset today (Monday, May 24).

The schemes this week include.

MONDAY.

Vulcan Road, Minehead: new gas main connection, lasting 34 working days.

Brunel Way, Minehead: new gas main connection, 23 working days.

Chilton Road, Burtle: drainage scheme, 10 working days.

Church Lane, Seavington St Mary: footways scheme, 10 workings days.

Marsh Lane, Tintinhull: vegetation clearance, nine working days.

Slade Lane, Old Cleeve: resurfacing scheme, five working days.

West Buckland Road, West Buckland: drainage works, five working days.

Peacehay Lane, Sampford Arundel: resurfacing preps, five working days.

Wood Road, Ashill: vegetation clearance, four working days.

Mill Lane, Brushford: resurfacing scheme, two working days.

WEDNESDAY.

Millbridge Road, Minehead: resurfacing scheme, two working days.

THURSDAY.

Forest Road, Frome: footway works, 20 working days.

FRIDAY.

Smokey Hole Lane, Chiselborough: resurfacing scheme, three working days.

Cadwells Lane, West Huntspill: install treatment plant outfall, three working days.

Orchard Close, North Petherton: resurfacing preps, two working days.