THE world’s first T-pylon - the first new design for an electricity pylon in Britain for nearly a century - has been installed in Somerset.
It will be one of 116 T-pylons along a 57km route, connecting low carbon energy to six million UK homes and businesses.
The pylons have a single pole and T-shaped cross arms which hold the wires in a diamond ‘earring’ shape.
They are 35 metres high, a third shorter than National Grid’s traditional lattice pylons, and have a smaller footprint, using less land.
UP T GOES: The pylon is installed near East Huntspill.
The new pylons form part of National Grid’s Hinkley Connection project, a £900million investment to connect low carbon electricity from Hinkley Point C nuclear power station.
They will run between Bridgwater and Portbury, other than through the Mendip Hills AONB, where the new connection goes underground.
The project also includes the removal of 249 electricity pylons between Bridgwater and Avonmouth.
The new pylon design was selected from more than 250 entries in an international competition run in 2011, organised by the Royal Institute of British Architects and the government (the then Department of Energy and Climate Change).
With a need for new energy infrastructure to enable progress towards net zero, the competition sought a new design to reduce impact on the local environment and surroundings.
T pylons form part of a suite of technologies used by National Grid to mitigate the impact of electricity infrastructure, including alternative lattice pylon designs and different types of underground and subsea cable systems.
The appropriate approach for each new development or upgrade is assessed on a case-by-case basis, with each technology used based where it is operationally possible and cost efficient for electricity consumers. Currently there are no other planned sections of T pylons.
Construction of the first 48 T-pylons by Balfour Beatty on behalf of National Grid began last week near East Huntspill, with each pylon taking roughly five days to build. Construction of the remaining 68 pylons, north of Sandford, will begin in 2022.
Chris Bennett, acting president of National Grid Electricity Transmission, said: “We are always looking for innovative new ways to mitigate the impact of our infrastructure on the natural environment and projects such as T pylons are a great example.
"This new design forms part of our significant investment in the network in England and Wales, adding capacity onto the grid to deliver increasing amounts of low carbon energy and support the UK’s drive towards its net zero target."
Matt Steele, Balfour Beatty’s managing director for its rail and utilities business, said: “Our unique capability and extensive experience in delivering major, complex overhead line schemes, makes us ideally positioned to play a key role in constructing the world’s first T-pylons.
“We look forward to working with National Grid to successfully and safely deliver low-carbon electricity to millions of people, supporting the UK’s net zero ambitions.”
The Hinkley Connection project will be ready to connect to Hinkley Point C by the end of 2024, with the project complete at the end of 2025.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here